Project History

Print
Press Enter to show all options, press Tab go to next option
Project Bar - Construction
Project History
Public Participation

Studies 

A project such as the Tenth Street Connector requires a great deal of coordination and technical analysis. The following schedule shows the tentative dates (subject to change) for the project’s deliverables and milestones:

  • 2008
    • Grade Separation Study (Sept)
    • Draft Preliminary Designs (Nov)
  • 2009
    • Citizens Informational Workshop (Apr)
    • Draft Environmental Assessment (Aug)
  • 2010
    • Final Environmental Assessment (Jan)
    • Citizens Informational Workshop (Mar)
    • Citizens Advisory Committee Meeting (June)
    • Citizens Advisory/Steering Committee Meeting (Aug)
    • NCDOT Public Hearing
      • (Tuesday, November 16, 2010)
        • Pre-Hearing Open House 4:30 p.m. - 6:30 p.m.
          Combined Public Hearing 7:00 p.m.
          Ronald G. Michels Center (2nd Floor)
          2335 Hemby Lane
          Greenville, NC 2783
  • 2011
    • Citizens Advisory Committee Meeting (Dec)
  • 2012
    • Field Inspection of Plans (Jan)
    • Design to NCDOT Right of Way Office (May)
    • Right of Way Office completes work plan and begins making contact (June)
      • Estimated time to complete right of way acquisition is 2 years
  • 2013
    • Utility Relocation Work Begins (Oct)
  • 2015
    • Project expected to begin Fall 2015